Which of the following statements are FALSE about the Rolling Wave plan?

Which of the following statements are FALSE about the Rolling Wave plan?

PrepAway - Latest Free Exam Questions & Answers

A.
Rolling Wave Planning is a phased iterative approach to project development.

B.
Rolling Wave Planning is a cost and schedule planning technique used in the Define Activities process.

C.
Rolling Wave Planning is the process of decomposing each work package within the WBS into the corresponding schedule activities required to produce the work package deliverables.

D.
Rolling Wave Planning describes a form of progressive elaboration planning where the work to be performed in the near time is planned in detail at a low level of the WBS, while work far in future is planned for WBS components that are relatively at a high level of WBS.