PrepAway - Latest Free Exam Questions & Answers

Which of the following situations will cause schedule activity duration estimates to directly influence the co

Which of the following situations will cause schedule activity duration estimates to directly influence the cost estimates EXCEPT:

PrepAway - Latest Free Exam Questions & Answers

A.
When resource cost rate information is unavailable from commercial databases

B.
When resources are applied per unit of time of duration of schedule activity

C.
When union labor with regularly expiring collective bargaining agreements are involve

D.
When seasonal cost variations are involve E. When project budget includes interest rate changes

One Comment on “Which of the following situations will cause schedule activity duration estimates to directly influence the co


Leave a Reply