Which of the following scheduling techniques incorporates a form of risk assessment?

A.
Arrow Diagramming Method (ADM)
B.
Program evaluation and Review Technique (PERT)
C.
Precedence Diagramming Method (PDM)
D.
Critical Path Method (CPM)
Explanation:
PERT : An event-oriented network analysis technique used to estimate project duration when there is a high degree of uncertainty with the individual activity duration estimates