Which of the following Project Scope Management processes involves subdividing the major project deliverables into smaller, more manageable components?
A. Collect Requirements
B. Initiation
C. Control Scope
D. Define Scope
2 Comments on “Which of the following Project Scope Management processes involves subdividing the major project deliverables ”
D
0
0
Isn’t it “create WBS” process?
0
0