Which of the following project document is best suited for tracking costs of resources?

A.
Work breakdown structure
B.
P’sk breakdown structure
C.
Organizational breakdown structure
D.
Resource breakdown structure
Explanation:
The resource breakdown structure organizes all resources in a hierarchical structure, allowing for cost tracking also.