Which of the following methods is a technique used to predict project duration by analyzing which sequence of activities has the least amount of scheduling flexibility?

A.
Dependency diagramming
B.
PERT
C.
Critical Path
D.
Grant chart
You must be logged in to post a comment.
I agree with the answer. C