Which of the following is true about a project charter?

A.
A project charter should be published under the name of a manager external to the project.
B.
A project charter should be published under the project sponsor’s name.
C.
A project charter should be published under the name of the project manager.
D.
A project charter should be published under the name of the project champion.
Explanation:
According to the PMBOK Guide, a project charter should be published by a manager external to the project but with sufficient power and authority to carry it off.