Which of the following is output of Direct and Manage Project Execution ?

Which of the following is output of Direct and Manage Project Execution ?

PrepAway - Latest Free Exam Questions & Answers

A.
Change requests.

B.
Responsibility assignment matrix

C.
Work breakdown structure

D.
Project character

Explanation:
Change requests , Deliverables and work performance information is output of Direct and Manage Project Execution.