Which of the following is not true about change requests?

A.
They always require additional funding.
B.
They happen while the project work is being done.
C.
They can be written or verbal.
D.
They can be requested by a stakeholder.
Explanation:
Change requests do not always require more money. Approved changes may require more funds, but not always.