Which of the following is NOT an input of Estimate Costs?

A.
Earn Value Analysis
B.
Scope Baseline
C.
Risk Register
D.
Human Resource Plan
Explanation:
Earned value analysis is used during the execution of the project to determine resource consumption versus planned
I choose A