Which is a technique for Define Activities?

A.
Rolling Wave Planning
B.
Mandatory Dependencies
C.
Arrow Diagramming Method [ADM
D.
Precedence Diagramming Method [PDM]
Explanation:
Rolling wave planning is a technique for Define Activities. Other options are technique for Sequence Activities.