When the project team directs staff assignments, which of the following is not considered in the selection of

When the project team directs staff assignments, which of the following is not considered in the selection of a staff?

PrepAway - Latest Free Exam Questions & Answers

A.
Previous experience

B.
staff age

C.
Availability

D.
Personal interest

Explanation:
Staff age is not considered in the selection of a staff