You are the project manager of a project .You have just completed the Collect Requirements and Define Scope. What should you do next?

PrepAway - Latest Free Exam Questions & Answers

A.
Create WBS

B.
Verify Scope

C.
Value analysis

D.
Control Scope

Explanation:
Create the WBS is the process that follows Collect Requirements and Define Scope.

6 Comments on “What should you do next?

  1. me says:

    Which of the following is an input required in the Define Scope process?

    a. A work breakdown structure
    b. An operational structure
    c. A process matrix
    d. Organizational process asset

    The answer is: d




    0



    0
  2. me says:

    Only one tool or technique is used to complete the Control Scope process. That tool is:

    a. Variance analysis
    b. Reserve analysis
    c. Trend analysis
    d. Regression analysis

    The answer is: a




    0



    0
  3. me says:

    You are a PM between projects and are taking a course that reviews information that has been developed regarding the ways in which people, teams, and organizational units behave. The course includes theories by Hertzog, Covey, Taylor and Maslow. Which Plan Human Resources tool or technique does your course address?

    a. Negotiation
    b. Expert judgment
    c. Organizational theory
    d. Roles and responsibilities

    The answer is: c




    0



    0
  4. me says:

    Why do milestones have zero duration when other project events exist for a measurable length of time?

    a. Milestones occur at random intervals within the project plan.
    b. Milestones represent a moment in time.
    c. Milestones are insignificant events within the structure of the project plan.
    d. Milestones cannot be predicted.

    The answer is: b