You are the project manager and have just completed the Collect Requirements and Define Scope process. What should you do next?

A.
Create WBS
B.
Verify Scope
C.
Value analysis
D.
Control Scope
Explanation:
Create the WBS is the process that follows Collect Requirements and Define Scope.