You are the project manager of a project. The project plan has been developed. A project end date has been established. The customer later requesters additional work to be included in the project, but will not renegotiate the end date. Cost is not a factor. What should the project team do immediately?

A.
Invoke the change control process
B.
Initiate contingency plans
C.
Modify the original project scope to include the additional work
D.
Commit to original project scope and open a new project to handle additional work
I agree with the answer. A