PrepAway - Latest Free Exam Questions & Answers

What should the project team do immediately?

You are the project manager of a project. The project plan has been developed. A project end date has been established. The customer later requesters additional work to be included in the project, but will not renegotiate the end date. Cost is not a factor. What should the project team do immediately?

PrepAway - Latest Free Exam Questions & Answers

A.
Invoke the change control process

B.
Initiate contingency plans

C.
Modify the original project scope to include the additional work

D.
Commit to original project scope and open a new project to handle additional work

One Comment on “What should the project team do immediately?


Leave a Reply