What is the lowest level in a work breakdown structure?

What is the lowest level in a work breakdown structure?

PrepAway - Latest Free Exam Questions & Answers

A.
Project task

B.
w�rl< package

C.
sow

D.
None

Explanation:
A work package is the lowest level of a work breakdown structure.