What involves determining what quantities are to be used to perform project activities.

A.
Resource planning
B.
Estimate Costs
C.
Determine Budget
D.
Control Costs
Explanation:
Resource planning :Planning , identifying, documenting, and assigning project roles, responsibilities, and reporting relationships to individuals or groups.