You are project manager of a project. During the process of selecting the sellers, you reject one vendor because it doesn’t have the manufacturing capability. This is an example of which selection tool?

A.
Weighting system
B.
Screening system
C.
Seller rating system
D.
Expert judgment
Explanation:
A screening system rejects sellers that does not meet minimum requirements for the project.