Your project is moving ahead of schedule. Management elects to incorporate additional quality testing into the project to improve the quality and acceptability of the project deliverable. This is an example of which one of the following?

A.
Scope creep
B.
Change control
C.
Quality Assurance
D.
Integrated Change Control
Explanation:
Additional quality testing will require additional time and resources for the project. This is an example of Integrated Change Control.
I have the same idea. D