You are the project manager of a project. Project is installing AC to hotel rooms. You have done project cost and time estimates, told the customer that the estimates provided will be accurate if the rooms meet the requirements like (wooden coated). This is an example of which of the following?

A.
Risk
B.
Assumption
C.
Constraint
D.
Budget
Explanation:
This is an example of an assumption because estimates provided will be accurate if the rooms meet the requirements like (wooden coated). A and C are incorrect because the scenario did not describe a risk or constraint.
Correct answer is B