During the planning phase of your project, your project team members have discovered another way to complete a portion of the project scope. This method is safer for the project team, but may cost more for the customer. This is an example of _______.

A.
Alternative identification
B.
“‘s^ assessment
C.
Alternative selection
D.
Product analysis
Explanation:
Alternative identification is a planning process to find alternatives to completing the project scope.