This is an example of _______.

During the planning phase of your project, your project team members have discovered another way to complete a portion of the project scope. This method is safer for the project team, but may cost more for the customer. This is an example of _______.

PrepAway - Latest Free Exam Questions & Answers

A.
Alternative identification

B.
“‘s^ assessment

C.
Alternative selection

D.
Product analysis

Explanation:
Alternative identification is a planning process to find alternatives to completing the project scope.