A schedule activity may start 5 days before the predecessor activity finishes. This is an example of ______________.

A.
Finish-to-Start
B.
Finish-to-Finish
C.
Start-to-Start
D.
Start-to-Finish
Explanation:
D is the correct answer. Finish-to-start: An activity must finish before the next activity begins. Finish-to-finish: An activity must finish before the next activity can finish. Start-to-start: An activity must start before the next activity can start. Start-to-finish: An activity must start before the next activity can finish.