The project baseline is:

A.
original plans plus the approved changes
B.
important in the project initiation phase
C.
initial estimates for tasks and resource utilization
D.
None
Explanation:
The project baseline : original plans plus the approved changes .
I have the same idea. A
0
0
The project baseline consists of the scope, schedule and cost baseline. Baselines are, in essence, the plans or estimates for each area. Therefore, either answer A or C could be considered correct. I would choose C.