The main purpose of project initiation is to ________.

A.
Assign the project manager to the project
B.
Formally describe the project
C.
Produce the project charter
D.
Formally authorize the project
Explanation:
Output of project initiation is formally authorizing the project. Output of project scope initiation is:
Project charter PM assigned Constraints and Assumptions.
I have the same idea. D