The Collect Requirements process is:

A.
Developing a plan from major stakeholders
B.
Developing a written scope statement as the basis for future project decisions
C.
Formalizing acceptance of the project scope
D.
Planning project milestones
Explanation:
Collect Requirements :Process of progressively elaborating and documenting the project work that produces the product of the project
Correct answer is B