Technical associations and consultants of a project are two examples of __________ ?

A.
Expensive additions
B.
Scope managers
C.
Expert judgment
D.
External Resources
Explanation:
C is the correct answer. Expert judgment is most effective way of dealing with questions concerning choices of projects. Expert Judgment: Expert judgment related to how equivalent projects have managed scope is used in developing the project scope management plan.
I have the same idea. C