Resource reallocation from non critical to critical activities is an example of which of the following Project Scheduling technique:

A.
Resource Leveling
B.
Schedule Compression
C.
Critical Path Method
D.
What if Analysis
Explanation:
Resource Leveling :Allocate scare resources to critical path activities first .
A