Project Managers have maximum authority in which type of organization?

A.
Weak Matrix organization
B.
Strong Matrix
C.
Balanced Matrix organization
D.
None
Explanation:
Weak Matrix : Power reset with Functional Manager.
Strong Matrix: Power rest with Project Manager.
Balanced Matrix :Power is shared between both Functional and Project Manager.
Correct answer is B