Parametric Estimating is done as a part of which of the following process:

A.
Develop Schedule
B.
Estimate Activity Durations
C.
Sequence Activities
D.
Estimate Activity Resources
Explanation:
Tools and Techniques for Estimate Activity Durations are : Analogous estimates , Parametric Estimating, Three-Point Estimates and Reserve Analysis.
I have the same idea. B