Most schedule simulations are based on some form of which of the following?

Most schedule simulations are based on some form of which of the following?

PrepAway - Latest Free Exam Questions & Answers

A.
DelPhi

B.
PERT

C.
CPM

D.
Monte Carlo Analysis