__________ involves using project characteristics in a mathematical model

A.
Analogous estimating
B.
Life-cycle costing
C.
Parametric modelling
D.
Bottom up estimating
Explanation:
Parametric modeling : Using project characteristics (or parameters) in a mathematical model to predict costs (e.g., price per square foot).