In which phase project manager is assigned to a project?

A.
During the initiation stage
B.
During the planning stage
C.
After approval of budget
D.
After the project is proven feasible
Explanation:
output of Initiation process : Project charter PM assigned Constraints Assumptions Project manager is assigned to a project During the initiation stage.