You are project manager of a project. A customer requests a scope change in the project . In order to determine the impact of the requested change, you will need a work breakdown structure, change request, scope management plan, and:

A.
Performance reports.
B.
A responsibility matrix.
C.
A Pareto diagram
D.
A Monte Carlo simulation.