If BCWP =400, ACWP = 410, and BCWS = 350, what is the cost performance index?

A.
0-413
B.
0-82
C.
1-06
D.
1-142
Explanation:
Cost Performance Index (CPI): The ratio of budgeted costs to actual costs (BCWP / ACWP). If CPI is less than 1, this means that the project is over budget.
I agree with the answer. D
0
0
These terms are from PMBOK 3rd edition, which is not tested on any more. Regardless, the supplied answers are all wrong.
BCWP == EV, ACWP == AC, BCWS == PV
CPI = EV / AC == 400 / 410 == 0.9756