If a project with a SPI of 0.8, what you tell?

A.
The project is running ahead of the schedule
B.
The project is running behind of the schedule
C.
Resources assigned to the project cost 1.8 units
D.
None
Explanation:
The SPI equals the earned value divided by the planned value. SPI = EV/PV A schedule performance index of 1 or greater suggests that the project is ahead of schedule.
Correct answer is B