If a project with a SPI of 0.8, what you tell?

If a project with a SPI of 0.8, what you tell?

PrepAway - Latest Free Exam Questions & Answers

A.
The project is running ahead of the schedule

B.
The project is running behind of the schedule

C.
Resources assigned to the project cost 1.8 units

D.
None

Explanation:
The SPI equals the earned value divided by the planned value. SPI = EV/PV A schedule performance index of 1 or greater suggests that the project is ahead of schedule.