Formal acceptance by the client or sponsor of the project should be prepared and distributed during which of the following process?

A.
Distribute Information
B.
Administrative Closure
C.
Organizational Planning
D.
Report Performance
Explanation:
Formal acceptance by the client or sponsor of the project should be prepared and distributed during Administrative Closure process
I agree with the answer. B
0
0