PrepAway - Latest Free Exam Questions & Answers

Duration estimates indicate:

Duration estimates indicate:

PrepAway - Latest Free Exam Questions & Answers

A.
How many work periods an activity is expected to last.

B.
How many hours a resource will work on an activity.

C.
When an activity is likely to finish.

D.
When an activity is likely to start.