Decomposition is ___________.

A.
What happens when changes to the project scope are ignore
B.
Subdividing the major project deliverables into smaller, more manageable components
C.
Defining a general product description into more discrete definitions of individual components
D.
Subdividing the project into logical divisions of effort aligned within the performing organization’s functional areas
B