Cost benefit analysis, scorecard modelling, payback periods, and internal rate of return are examples of ____________.

A.
Enterprise benefits measurement methods when selecting a project
B.
Integral parts of the SOW
C.
Ways to ensure stakeholder commitment
D.
Project selection methods
Explanation:
Projects are seeded from the recognition of a regulatory or business need. Cost benefit analysis, scorecard modelling , payback periods, and internal rate of return are examples of benefits measurement methods when selecting a project. Best Option is A.
Disagree. I beleive its D. A doesn’t make any sense to me as it asks for examples of.