Contingency planning is a means to _____ risks to the project through a formal process and provides the resources to meet the risk events.

A.
Address
B.
Classify
C.
Assign
D.
Resolve
Explanation:
Contingency Planning :The development of a management plan that identifies alternative strategies to be used to ensure project success if specified risk events occur.