Collect Requirements process starts in Project Planning Phase and uses the outputs of the __________.

A.
Initiation Process
B.
Project closer Process
C.
Estimation Process
D.
Closing process
Explanation:
Collect Requirements process starts in “Project Planning Phase” and uses the outputs of the Initiation Process.
Correct answer is A