At which stage, stakeholders have the maximum influence on a project?

A.
Initial stage
B.
Closing stage
C.
Execution stage
D.
None of the above
Explanation:
It is easy to make changes to project goals and approach at the initial stage. Stake holders have maximum influence at Initial stage.