All of the following statements about the project charter are correct except:

A.
It Is often an internal legal document.
B.
It identifies the project manager’s authority and responsibility.
C.
It identifies management and/or customer approved scope of the project.
D.
It usually does not identify cost and time estimates.
Explanation:
Project charter includes budget summary and summary milestone schedule also.