All are output of verify scope.

A.
Precedence diagramming method (PDM)
B.
Arrow diagramming method (ADM)
C.
Expert judgment
D.
Network templates
Explanation:
Expert judgment is not used in Sequence Activities.
Sequence Activities : Identifying and documenting interactivity logical relationships.