During the execution of a software project, the vendor proposes an upgrade of a part of project without a change in the schedule or cost. After the change is approved, where would this change BEST be documented?

A.
Project charter
B.
Procurement Management plan
C.
Work breakdown structure
D.
Quality assurance plan
I have the same idea. B