Administrative Closure should occur ___________.

A.
At the end of each phase of the project
B.
At the end of the whole project
C.
At the end of 50% of the project
D.
At the end of 100% of the project
Explanation:
Administrative Closure should occur at the end of each phase, not only at the end of the overall project