According to the PMBOK Guide, the project statement of work (SOW) should contain or reference all the followin

According to the PMBOK Guide, the project statement of work (SOW) should contain or reference all the following elements except?

PrepAway - Latest Free Exam Questions & Answers

A.
Business need, strategic plan, and product scope description

B.
Requirements, business need, and stakeholder expectations

C.
Strategic plan, product scope description, stakeholder influences, and business need

D.
Project purpose, business case, stakeholder influences, and product scope description

Explanation:
The project SOW should contain the business need for the project and the product scope description and should support the organization’s strategic plan.