According to the PMBOK Guide, the project statement of work (SOW) should contain or reference all the following elements except?

A.
Business need, strategic plan, and product scope description
B.
Requirements, business need, and stakeholder expectations
C.
Strategic plan, product scope description, stakeholder influences, and business need
D.
Project purpose, business case, stakeholder influences, and product scope description
Explanation:
The project SOW should contain the business need for the project and the product scope description and should support the organization’s strategic plan.
I disagree with the answer, the question says ‘all elements ‘EXCEPT’? That means which are not included in SOW and answer A shows whose are included.
1
0
I meant ‘those are included’
1
0