According a PERT weighted average computation, what is the probability of completing the project within plus-or-minus 3 standard deviations of the mean?
A. 68%
B. 99.74%
C. 95%
D. 75%
One Comment on “According a PERT weighted average computation, what is the probability of completing the project within plus-o”
I agree with the answer. B