A scope management plan In which of the following scope management processes is the scope management plan prep

A scope management plan In which of the following scope management processes is the scope management plan prepared?

PrepAway - Latest Free Exam Questions & Answers

A.
Initiation

B.
Collect Requirements

C.
Define Scope

D.
Verify Scope