PrepAway - Latest Free Exam Questions & Answers

A response to a risk event that was not defined in advance of is occurrence is called a:

A response to a risk event that was not defined in advance of is occurrence is called a:

PrepAway - Latest Free Exam Questions & Answers

A.
Risk mitigation response.

B.
Workaround response.

C.
Corrective action response.

D.
Contingency response.

One Comment on “A response to a risk event that was not defined in advance of is occurrence is called a:


Leave a Reply